I would rather bring five explainable measures to a delivery meeting than twenty attractive numbers whose meaning changes under questioning. The dashboard needs to help someone decide what happens next. It should not reward the team for producing more files while accepted work remains stuck.
My example is a fictional training-content programme with twelve planned learning items. Eight have a first draft, five have completed review and four are accepted for release. Those counts describe different stages. I would not combine them into a single progress percentage without explaining what it measures.
I name the unit being counted

The first label would say learning items, not assets, unless assets are genuinely the agreed unit. One learning item may contain a video, a transcript and supporting images. Counting those files as separate completed outcomes could make production volume look like delivery progress.
I would keep the denominator visible beside each count. Four accepted items out of twelve planned is a different statement from four accepted items out of five reviewed. Both may be useful, but they answer different questions and should not share an unexplained percentage.
I show the age of unresolved work

A total of three items in review does not tell me whether they arrived this morning or have been waiting for two weeks. I would include the oldest unresolved review and the next decision it needs, with an owner and a date for that decision.
I would distinguish elapsed waiting time from the effort required to complete the review. That prevents a long wait from being interpreted automatically as a difficult task. The appropriate response could be to clarify the request or arrange access rather than add another editor.
I keep status understandable without colour
I would use text labels and clear grouping alongside colour. The W3C explanation of WCAG's use-of-colour criterion says that colour should not be the only visual means of conveying information. W3C use of colour.

For the fictional programme, a row would say waiting for subject review rather than rely on an amber dot. The label gives the meeting a starting point and remains meaningful in a monochrome export or to someone who perceives colours differently.
I separate current evidence from forecast
The dashboard might show four accepted items now and a forecast of six by Friday. I would label the second figure as a forecast and state the assumptions behind it. Two available review windows and complete source material might be necessary for that forecast to hold.

If either assumption changes, the forecast needs revision. I would not keep an outdated projection because it looks more encouraging than the current evidence. A useful delivery review should make uncertainty discussable before it becomes a missed commitment.
I end with decisions and owners
Each exception should lead to a clear question. Does a reviewer need to resolve conflicting feedback? Does the owner need to choose a smaller first release? Is a missing source preventing the next stage? The dashboard should link to the relevant record without forcing everyone through the whole project history.

After the meeting, I would record the decisions and update the affected commitments. If the discussion produces no action or understanding, I would reconsider which measures deserve space on the next dashboard. The aim is not a perfect-looking report; it is a better-informed delivery decision.
Research and example note
Prepared for 15 November 2026. All counts and programme details are fictional. W3C supports only the colour-independent communication principle. The proposed measures are not client performance results or a universal reporting standard.